Seven Mills sign above a decorative screen beside landscaped planting, seating and a paved walkway.

Project Overview

Seven Mills is Cairn Homes’ new town in Dublin 22, situated along the Grand Canal between Lucan and Clondalkin. Construction began in January 2023, with the first residents moving into Parkleigh later that year.

Already home to more than 4,000 people, the development is planned to provide approximately 5,500 homes for up to 15,000 residents, alongside schools, shops, community amenities and 225 acres of green space.

Problem

Cairn Homes needed charging infrastructure that could grow alongside a development being delivered in phases.

The initial requirement was to provide charging capacity for approximately 20% of parking spaces, while preparing for future provision across all spaces. On-street and underground parking created different installation requirements, while fitting out every space immediately would have required substantial upfront cabling, ducting and electrical works.

Limited Wi-Fi coverage in parts of the development also made dependable charger connectivity essential.

Seven Mills – Zaptec Pro Residential Charging

Solution

Solutions EV worked with Cairn Homes and Zaptec to design and install a phased charging system using Zaptec Pro.

The infrastructure allows additional chargers to be introduced as demand grows, reducing unnecessary upfront cabling and ducting while preparing future parking spaces to come online efficiently.

The project combines Solutions EV’s design, installation and ongoing technical support with Zaptec’s scalable charging technology.

Solutions EV worked with Cairn Homes and Zaptec to design and install a phased charging system using Zaptec Pro.  The infrastructure allows additional chargers to be introduced as demand grows, reducing unnecessary upfront cabling and ducting while preparing future parking spaces to come online efficiently.  The project combines Solutions EV’s design, installation and ongoing technical support with Zaptec’s scalable charging technology.

Connectivity and Support

Zaptec Pro’s integrated 4G LTE connectivity allows chargers to connect through built-in SIM cards, without relying on local Wi-Fi.

Through the Zaptec portal, Solutions EV can monitor performance, review system status and identify potential issues remotely. Remote diagnostics also allow certain faults to be resolved without an immediate site visit, supporting the charging network as Seven Mills expands.

seven-mills-solutions-ev-zaptec-pro-delivery.jpg

Result

Approximately 350 Zaptec Pro chargers had been installed at the time of this case study.

Cairn Homes now has a connected charging system that meets current requirements and provides a pathway towards charging across all parking spaces.

Phased delivery reduces unnecessary upfront infrastructure, while integrated connectivity and remote monitoring support the network as the community grows.

seven-mills-residential-ev-charging-in-use.jpg

Building EV charging infrastructure for a town that is still growing.

Seven Mills demonstrates how phased EV charging can meet today’s needs while preparing for tomorrow.

Through early planning and collaboration between Cairn Homes, Solutions EV and Zaptec, the charging system can expand alongside a town planned for up to 15,000 residents.

Seven Mills – Community and Green Spaces